Refurbishment of Staff Welfare and Ticket Office Areas at Subway Station

The project:

Background:

We were appointed to SPT’s Minor Works Framework in 2022 to deliver various small works and maintenance projects across their subway stations. We were approached as part of a mini-competition tender exercise for this project to upgrade the ticket office and welfare facilities at Partick Subway Station.

Scope of works:

  • Phased Project Delivery:
    • Phase 1: Scotrail Staff Welfare Facilities
    • Phase 2: SPT Staff Welfare Facilities
    • Phase 3: Ticket Office Works (concurrent with Phases 1 & 2, night shift)
  • Welfare Facility Works (Phases 1 & 2):
    • Safe isolation and strip-out of existing facilities.
    • Installation of Altro Whiterock wall linings.
    • Installation of new kitchen units.
    • Works to ceilings, tiles, and services.
    • Decoration of doors and woodwork.
    • Replacement of floor coverings.
    • Installation of new sanitaryware.
  • Ticket Office Works (Phase 3):
    • Painting and decoration.
    • Replacement of floor coverings.
  • General Project Execution:
    • All works completed by in-house skilled tradespeople.
    • On-site supervision by a dedicated Site Supervisor.
    • Station and ticket office remained operational throughout the project.
    • Minimised disruption to ticket office by completing phase 3 at night.

 Challenges:

This project demanded thorough planning and coordination to execute night-shift tasks while keeping the station fully operational. We maintained consistent communication with Scotrail and SPT stakeholders, ensuring that all work was completed without affecting station operations.

Our skilled in-house team of tradespeople managed the tasks, focusing on cost control and quality assurance. 

We organised night-shift activities to reduce disruption to ticket office operations. 

We partnered with the client’s HSEQ department to guarantee adherence to the highest safety standards.